Green Energy at netcup
29.09.2026|Category: Sustainability

netcup is part of the Austrian Anexia Group, which generates some of the electricity for its data centers itself. Two hydroelectric power plants in Styria (Kammern, Fressnitz) and a solar park in Lower Austria (Jaidhof) together generate approximately 2.2 megawatts of power.
Kammern feeds power directly into the Vienna data center (Datasix), where netcup servers are also located. This article reveals how much electricity comes from in-house generation, which facilities are involved, and what the limitations are regarding available data.

Plant
Type
Location
Capacity
Status
Annual Output
Kammern
Run-of-river hydropower plant, Kaplan turbine
Liesingtal, Styria
600 kW
Transferred on May 10, 2024
Not published
Fressnitz
Run-of-river hydropower plant, Pelton turbine
Fressnitzbach, Krieglach district, Styria
Around 600 kW (according to Anexia Energy)
Different owner until end of October 2025, since then Hydro Power Fressnitz GmbH, a subsidiary of Anexia Energy
Not published
Jaidhof
Ground-mounted photovoltaic system, 1,428 solar modules
Krems Land, Lower Austria
Around 1 MW
Built in 2025
Around 1,127 MWh per year
Only for the Jaidhof solar park is the annual output publicly disclosed, around 1,127 MWh per year. No published figures exist for Kammern or Fressnitz, so the combined total of all three plants is likely higher than this number.
The Kammern hydropower plant was transferred to Anexia on May 10, 2024, the group's first in-house generation facility. According to Alexander Windbichler, around 12,000 tons of water plunge through a pressure pipeline every second, using a drop in the 40-kilometer Liesing river. The electricity flows directly into the operation of Anexia's data centers, above all into the Vienna data center Datasix, to which netcup is connected as a subsidiary.



Fressnitz was added as the third plant after Kammern and Jaidhof and, according to Anexia Energy, generates around 600 kW. Design flow rate, head, and the pressure pipeline are not publicly documented in detail. The company behind it belonged to a different owner until the end of October 2025 and has since operated as Hydro Power Fressnitz GmbH, a wholly owned subsidiary of Anexia Energy.
Native shrubs were planted around the Jaidhof solar park, along with a wildflower meadow that is mowed only once a year, creating habitat for flora and fauna in this intensively farmed agricultural area.
Metric
Unit
2022
2023
2024
Total greenhouse gas emissions
t CO2 equivalent
713.76
701.38
924.59
Office energy consumption (electricity and heat)
MWh
300.19
345.48
394.16
Source: 2025 Environmental Report, Anexia Group, key figures based on EMAS core performance indicators, first collected in 2025.
Total emissions rose in 2024, according to the environmental report mainly due to increased demand for data center hardware. Looked at in isolation, excluding data centers and employee mobility, the corporate carbon footprint of on-site activities fell by 7 percent in 2024. The 2024 target of an overall 5 percent reduction was therefore missed overall.
As one of the measures for the 2025 goals, the environmental report names, among other things, the purchase of additional power plants and an improved energy mix at further data center locations.
These figures are targets for 2025, not confirmed actual values. Whether they were achieved will likely only be published in the next environmental report.


netcup has been certified to ISO 14001, the environmental management standard, since 2023, the Anexia Group as a whole since 2022 already. Both certificates are audited annually by TÜV Nord Cert GmbH. netcup and Anexia also hold further certificates for quality, information security, and data protection, details on the netcup certifications page.
For private and smaller hosting customers, nothing changes about the product, the green power share is part of the existing infrastructure and not an add-on tariff. For business customers with their own sustainability reporting, for example under CSRD, the ISO 14001 certificate and the annual environmental report can serve as supplier evidence. One trade-off remains: the figures apply at group level, there is currently no way to calculate one's own server consumption individually against the power plant output.
The figures in this article come from public Anexia and netcup sources. All values are group-level figures for the Anexia Group, not netcup-specific measurements. The full list of sources with links and access dates is at the end of the article.